| 1. | Dams more than 6 ft high fall under TCEQ jurisdiction and are to comply with TCEQ regulations on dam safety regardless of whether the TCEQ requires a water right for the impoundment. | 
|  |  | True | 
|  |  | False | 
| 2. | A failure would be considered an unintended release of impounded water due to the loss of all or a portion of the dam or affiliated structure. | 
|  |  | True | 
|  |  | False | 
| 3. | All freeboard calculations should include the expected future settlement and consolidation of the embankment after construction in addition to wave run-up. | 
|  |  | True | 
|  |  | False | 
| 4. | The intent of the precipitation analysis is to find the _____________________ that would produce the most critical loading on the dam. | 
|  |  | Critical storm size, | 
|  |  | Location, | 
|  |  | Orientation, | 
|  |  | Duration, | 
|  |  | All the above | 
|  |  | None of the above | 
| 5. | The PMP depths for a particular storm size and range of storm durations are not used to determine the critical storm duration for a dam. | 
|  |  | True | 
|  |  | False | 
| 6. | The Snyder Unit Hydrograph Method and the NRCS Dimensionless Unit Hydrograph Method are the two commonly used precipitation loss methods. | 
|  |  | True | 
|  |  | False | 
| 7. | NRCS Hydrologic Soil Groups and Uniform Infiltration (Loss) Rates are shown in _________. | 
|  |  | Figure 5.1 | 
|  |  | Figure 5.2 | 
| 8. | Typically, two parameters are needed to develop a Snyder Unit Hydrograph and they are _________. | 
|  |  | TL, lag time & T lead time | 
|  |  | Cp, shape factor & T lead time | 
|  |  | Cp, shape factor & TL, lag time | 
| 9. | How many parameters are used in the NRCS Unit Hydrograph method? | 
|  |  | One | 
|  |  | Two | 
|  |  | Three | 
| 10. | In models that require routing of the design-storm runoff hydrographs through a stream channel, either a hydrologic or hydraulic routing method may be used. These hydrologic methods are either empirical or semi-empirical. | 
|  |  | True | 
|  |  | False | 
| 11. | Level Pool Routing is the most typically used method for routing a hydrograph through a reservoir in hydrologic models. | 
|  |  | True | 
|  |  | False | 
| 12. | The con in a Kinematic Wave streamflow routing method is that the parameters cannot be estimated from field observations. | 
|  |  | True | 
|  |  | False | 
| 13. | Emergency spillways are generally cut into an abutment and have little or no erosion protection from flows discharging through them. | 
|  |  | True | 
|  |  | False | 
| 14. | ______________________ is a hydrologic condition where the inflow hydrograph is equal to the full design flood. | 
|  |  | Design-flood breach | 
|  |  | Sunny-day breach | 
| 15. | The __________________is determined by the equation (Eq 8.3), which is                           LU = 0.012 * KS * sq root [ 2*C  *H ] | 
|  |  | Inundation length in miles | 
|  |  | Total discharge from the breach | 
| 
 |